← Inventory
ASM-BKT-DRV
MakeBucket Drive Assembly
Assembly · drawing BD-BKT-DRV rev B · made at Assembly Bay
On hand
1ea
B-07-3 · Archerfield Workshop WIP
Allocated
0
Committed to jobs
Free
1
Reorder point —
On order
0
35-day lead
Turns
8.0
8 ea a year
Value held
$47,214
$47,214.04 each
Raise now
Needed 7 Sep 2026, and the 35-day lead means it should already have left — expedite by 1 days
Driven by WO-2026-0438 (1 ea by 7 Sep 2026), WO-2026-0442 (1 ea by 1 Oct 2026) .
Stock movements
Newest first. The balance on the top row is the on-hand figure above — the ledger and the position can't disagree, because one is derived from the other.
| Date | Type | Reference | By | Qty | Balance |
|---|---|---|---|---|---|
| No movements recorded against this part yet. | |||||
Costing
- Material rolled up
- $29,160.04
- Labour (153 h)
- $18,054.00
- Standard cost
- $47,214.04
- Lead time
- 35 days
Where used
Goes into 3 structures.