Good morning, Craig
Every figure below is the sum of rows you can open — and every one of them is live. Nothing on this page was exported, pasted into a spreadsheet or rebuilt in Power BI.
Order book
$11.2M
Work in progress
$3.23M
Invoiced FY27 to date
$2.97M
Quotes out
$4.79M
Debtors
$2.47M
Stock on hand
$2.12M
Below reorder point
38
Jobs on time
89%
Shop load this week
Scheduling →Week commencing 3 Aug 2026. Red is over capacity.
Order book by family
Ex GST, by promise month.
Order book, by the month it's promised
Sales orders →$11,201,326.00 ex GST across 14 confirmed orders.
Needs you today
9-
WO-2026-0431 stuck at Bodycote Australasia
Operation 50, Heat treatment — harden and temper. Promised 8 Aug 2026, 4 days ago.
-
WO-2026-0401 past its promise date
Bournedrill THD350 for Bauer Foundations Australia. Due 31 Jul 2026, 66% booked.
-
WO-2026-0396 past its promise date
Bournedrill 2000R for McConnell Dowell Constructors. Due 3 Aug 2026, 66% booked.
-
8 parts at zero
ACC-TRI-1200, ACC-CH-600, GBX-THD-1000 and 5 more. Run requirements before raising anything.
-
9 reorder points tripped with no requirement behind them
$235,127 the levels say buy today. The schedule says it isn't needed. Deferred, with the date on each line.
-
INV-2026-0616 is 12 days overdue
Coastal Water Bores, $270,067.60 inc GST. Due 23 Jul 2026.
-
INV-2026-0584 is 27 days overdue
Pilecorp Pty Ltd, $187,855.80 inc GST. Due 8 Jul 2026.
On the floor right now
All work orders →| Work order | Building | For | Operation | Hours | Progress | Value | Due |
|---|---|---|---|---|---|---|---|
| WO-2026-0429 | BD-5000R Bournedrill 5000R | Keller Australia | Robotic weld — mast box and chassis frame Robotic Weld Cell | 237 / 1,954 | 12% | $1,220,000 | Fri 27 Nov |
| WO-2026-0396 | BD-2000R Bournedrill 2000R | McConnell Dowell Constructors | Assembly — drive, power pack, undercarriage Assembly Bay | 1,069 / 1,654 | 66% | $1,030,000 | Mon 3 Aug |
| WO-2026-0408 | BD-2000THD Bournedrill 2000THD | Vibropile (Aust) Pty Ltd | Test and commission — load and function test Test & Commission | 1,734 / 1,635 | 97% | $1,010,000 | Fri 7 Aug |
| WO-2026-0401 | BD-THD350 Bournedrill THD350 | Bauer Foundations Australia | Assembly — drive, power pack, undercarriage Assembly Bay | 1,053 / 1,623 | 66% | $1,005,000 | Fri 31 Jul |
| WO-2026-0412 | BD-1500RC Bournedrill 1500RC | Piling Contractors Pty Ltd | Blast and 2-pack — Bournedrill navy Paint Booth | 1,556 / 1,549 | 92% | $945,000 | Fri 14 Aug |
| WO-2026-0436 | BD-1000THD Bournedrill 1000THD | Frankipile Australia | Robotic weld — mast box and chassis frame Robotic Weld Cell | 164 / 1,379 | 12% | $870,000 | Fri 6 Nov |
Your pinned reports
Reports →Built here, not in Excel. They read the same rows the modules do.
Recent activity
All activity →- 07:12 Spindle overdue at Bodycote Purchasing
WO-2026-0431 op 50 promised 24 Jul, still out at 19 days against a 12-day lead. The 500RC test date moves if it isn't back this week.
- 06:58 9 parts below reorder point Inventory
Including 2 at zero — the D5 undercarriage and the 2000-series gearbox. Run requirements before raising anything.
- 16:40
THD25 with two auger heads and eight drill pipes. Waiting on Shane's bore schedule before the mast length is firm.
- 15:05
Central Drilling Solutions, S350 well-service unit. Deposit 40%, promised 30 Oct.
- 11:22 PO-2026-0448 raised — Cummins QSB6.7 × 2 Purchasing
84-day lead. This is the binding constraint on WO-2026-0441 and every 1000-series rig behind it.
- 09:40 INV-2026-0584 is 57 days overdue Invoicing
Pilecorp, $121,880 including GST. Chased twice. Craig to call Sam.