Bournedrill
Bournedrill
WO-2026-0430 Demo Drill Pipe 114 mm × 3 m × 40
Xero connected Tue 4 Aug 2026
← Work orders

WO-2026-0430

In progress

ACC-DP-114-3M — Drill Pipe 114 mm × 3 m × 40

Stock build · started 6 Jul 2026 · due 14 Aug 2026 · Ryan Beattie

Sell value

$92,400

At list

Material

$33,120

3 leaf lines

Labour booked

$18,762

159 h at $118.00

Hours vs plan

-61

159 booked of 220 planned

Margin as it stands

43.9%

$40,518 · quoted at $33,320

Routing

5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.

Operation 4 of 5
Op Operation Work centre / supplier Start Finish Planned h Booked h Var By Status
10 Cut and prep bar and tube Cut & Prep
Plasma table, band saws, drill line
Mon 6 Jul Sat 11 Jul 31 31 0 Complete
20 CNC turn and mill CNC Machining
Horizontal borer, 2 × CNC lathe, VMC
Sat 11 Jul Sun 26 Jul 101 108 +7 RB Complete
30 Heat treatment — harden and temper Bodycote Australasia
Outside operation · 12-day lead · 87% on time
Sun 26 Jul Fri 7 Aug EXT Complete
40 Weld, hardface and dress On now Fabrication Bay 2
Sub-assembly and accessory fabrication
Fri 7 Aug Fri 14 Aug 48 20 RB In progress
50 Assemble and inspect Assembly Bay
Rig build-up, 4 bays
Fri 14 Aug Thu 20 Aug 40 Planned

Kit list — what this job consumes

The bill of materials flattened to its leaves for 40 × ACC-DP-114-3M. 3 lines, $33,120.00 of material. 1 can't be covered from free stock today.

Full multi-level BOM →
Part No.DescriptionSourceSupplierRequiredFreeUnitExtended
SUB-HT-4140 Heat Treatment — 4140, harden & temper Subcontract Bodycote Australasia 40 ea 0 $420 $16,800
RAW-TUBE-114X10 Seamless Tube 114 × 10 Buy Bohler Uddeholm Australia 124 m 238 $124 $15,376
CON-WIRE-ER70S MIG Wire ER70S-6 1.2 mm Buy Cigweld 80 kg 424 $12 $944