← Work orders
WO-2026-0430
In progressACC-DP-114-3M — Drill Pipe 114 mm × 3 m × 40
Stock build · started 6 Jul 2026 · due 14 Aug 2026 · Ryan Beattie
Sell value
$92,400
At list
Material
$33,120
3 leaf lines
Labour booked
$18,762
159 h at $118.00
Hours vs plan
-61
159 booked of 220 planned
Margin as it stands
43.9%
$40,518 · quoted at $33,320
Routing
5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.
Operation 4 of 5
| Op | Operation | Work centre / supplier | Start | Finish | Planned h | Booked h | Var | By | Status |
|---|---|---|---|---|---|---|---|---|---|
| 10 | Cut and prep bar and tube | Cut & Prep Plasma table, band saws, drill line | Mon 6 Jul | Sat 11 Jul | 31 | 31 | 0 | — | Complete |
| 20 | CNC turn and mill | CNC Machining Horizontal borer, 2 × CNC lathe, VMC | Sat 11 Jul | Sun 26 Jul | 101 | 108 | +7 | RB | Complete |
| 30 | Heat treatment — harden and temper | Bodycote Australasia Outside operation · 12-day lead · 87% on time | Sun 26 Jul | Fri 7 Aug | — | — | — | EXT | Complete |
| 40 | Weld, hardface and dress On now | Fabrication Bay 2 Sub-assembly and accessory fabrication | Fri 7 Aug | Fri 14 Aug | 48 | 20 | — | RB | In progress |
| 50 | Assemble and inspect | Assembly Bay Rig build-up, 4 bays | Fri 14 Aug | Thu 20 Aug | 40 | — | — | — | Planned |
Kit list — what this job consumes
The bill of materials flattened to its leaves for 40 × ACC-DP-114-3M. 3 lines, $33,120.00 of material. 1 can't be covered from free stock today.
| Part No. | Description | Source | Supplier | Required | Free | Unit | Extended |
|---|---|---|---|---|---|---|---|
| SUB-HT-4140 | Heat Treatment — 4140, harden & temper | Subcontract | Bodycote Australasia | 40 ea | 0 | $420 | $16,800 |
| RAW-TUBE-114X10 | Seamless Tube 114 × 10 | Buy | Bohler Uddeholm Australia | 124 m | 238 | $124 | $15,376 |
| CON-WIRE-ER70S | MIG Wire ER70S-6 1.2 mm | Buy | Cigweld | 80 kg | 424 | $12 | $944 |