Bournedrill
Bournedrill
WO-2026-0432 Demo Kelly Bar Section — 3 m × 8
Xero connected Tue 4 Aug 2026
← Work orders

WO-2026-0432

On hold

MCH-KELLY-BAR-3 — Kelly Bar Section — 3 m × 8

Stock build · started 13 Jul 2026 · due 21 Aug 2026 · Nathan Poole

Note: On hold — 219 × 16 tube is short. Sitting on PO-2026-0431, due 12 Sep.

Sell value

$32,213

At list

Material

$11,445

2 leaf lines

Labour booked

$11,682

99 h at $118.00

Hours vs plan

-78

99 booked of 177 planned

Margin as it stands

28.2%

$9,086 · quoted at $0

Routing

5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.

Operation 3 of 5
Op Operation Work centre / supplier Start Finish Planned h Booked h Var By Status
10 Cut and prep bar and tube Cut & Prep
Plasma table, band saws, drill line
Mon 13 Jul Sat 18 Jul 25 25 0 Complete
20 CNC turn and mill CNC Machining
Horizontal borer, 2 × CNC lathe, VMC
Sat 18 Jul Sun 2 Aug 81 74 -7 NP Complete
30 Heat treatment — harden and temper On now Bodycote Australasia
Outside operation · 12-day lead · 87% on time
Sun 2 Aug Fri 14 Aug EXT On hold
40 Weld, hardface and dress Fabrication Bay 2
Sub-assembly and accessory fabrication
Fri 14 Aug Fri 21 Aug 39 Planned
50 Assemble and inspect Assembly Bay
Rig build-up, 4 bays
Fri 21 Aug Thu 27 Aug 32 Planned

Kit list — what this job consumes

The bill of materials flattened to its leaves for 8 × MCH-KELLY-BAR-3. 2 lines, $11,444.80 of material. 2 can't be covered from free stock today.

Full multi-level BOM →
Part No.DescriptionSourceSupplierRequiredFreeUnitExtended
RAW-TUBE-219X16 Seamless Tube 219 × 16 Buy Bohler Uddeholm Australia 24.8 m 12 $326 $8,085
SUB-HT-4140 Heat Treatment — 4140, harden & temper Subcontract Bodycote Australasia 8 ea 0 $420 $3,360