← Work orders
WO-2026-0432
On holdMCH-KELLY-BAR-3 — Kelly Bar Section — 3 m × 8
Stock build · started 13 Jul 2026 · due 21 Aug 2026 · Nathan Poole
Note: On hold — 219 × 16 tube is short. Sitting on PO-2026-0431, due 12 Sep.
Sell value
$32,213
At list
Material
$11,445
2 leaf lines
Labour booked
$11,682
99 h at $118.00
Hours vs plan
-78
99 booked of 177 planned
Margin as it stands
28.2%
$9,086 · quoted at $0
Routing
5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.
Operation 3 of 5
| Op | Operation | Work centre / supplier | Start | Finish | Planned h | Booked h | Var | By | Status |
|---|---|---|---|---|---|---|---|---|---|
| 10 | Cut and prep bar and tube | Cut & Prep Plasma table, band saws, drill line | Mon 13 Jul | Sat 18 Jul | 25 | 25 | 0 | — | Complete |
| 20 | CNC turn and mill | CNC Machining Horizontal borer, 2 × CNC lathe, VMC | Sat 18 Jul | Sun 2 Aug | 81 | 74 | -7 | NP | Complete |
| 30 | Heat treatment — harden and temper On now | Bodycote Australasia Outside operation · 12-day lead · 87% on time | Sun 2 Aug | Fri 14 Aug | — | — | — | EXT | On hold |
| 40 | Weld, hardface and dress | Fabrication Bay 2 Sub-assembly and accessory fabrication | Fri 14 Aug | Fri 21 Aug | 39 | — | — | — | Planned |
| 50 | Assemble and inspect | Assembly Bay Rig build-up, 4 bays | Fri 21 Aug | Thu 27 Aug | 32 | — | — | — | Planned |
Kit list — what this job consumes
The bill of materials flattened to its leaves for 8 × MCH-KELLY-BAR-3. 2 lines, $11,444.80 of material. 2 can't be covered from free stock today.
| Part No. | Description | Source | Supplier | Required | Free | Unit | Extended |
|---|---|---|---|---|---|---|---|
| RAW-TUBE-219X16 | Seamless Tube 219 × 16 | Buy | Bohler Uddeholm Australia | 24.8 m | 12 | $326 | $8,085 |
| SUB-HT-4140 | Heat Treatment — 4140, harden & temper | Subcontract | Bodycote Australasia | 8 ea | 0 | $420 | $3,360 |