← Inventory
FAB-CHS-FRAME-1000
MakeChassis Frame — 1000 class, welded
Fabrication · drawing BD-F-CHS-1000 rev D · made at Robotic Weld Cell
On hand
0ea
BAY 1 · Archerfield Workshop WIP
Allocated
0
Committed to jobs
Free
0
Reorder point —
On order
0
24-day lead
Turns
—
17 ea a year
Value held
$0
$21,857.40 each
Raise now
Needed 4 Aug 2026, and the 24-day lead means it should already have left — expedite by 24 days
Driven by (make ASM-CHS-TRK-D5) (3 ea by 4 Aug 2026), WO-2026-0440 (2 ea by 10 Sep 2026) .
Stock movements
Newest first. The balance on the top row is the on-hand figure above — the ledger and the position can't disagree, because one is derived from the other.
| Date | Type | Reference | By | Qty | Balance |
|---|---|---|---|---|---|
| No movements recorded against this part yet. | |||||
Costing
- Material rolled up
- $4,393.40
- Labour (148 h)
- $17,464.00
- Standard cost
- $21,857.40
- Lead time
- 24 days
Where used
Goes into 1 structure.