MakeChassis Frame — 500 class, welded
Fabrication · drawing BD-F-CHS-500 rev C · made at Robotic Weld Cell
On hand
1ea
BAY 1 · Archerfield Workshop WIP
Allocated
1
Committed to jobs
Free
0
Reorder point —
On order
0
21-day lead
Turns
13.0
13 ea a year
Value held
$15,774
$15,774.40 each
Raise now
Needed 4 Aug 2026, and the 21-day lead means it should already have left — expedite by 21 days
Driven by (make ASM-CHS-TRK-D3) (7 ea by 4 Aug 2026) .
Stock movements
Newest first. The balance on the top row is the on-hand figure above — the ledger and the position can't disagree, because one is derived from the other.
| Date | Type | Reference | By | Qty | Balance |
|---|---|---|---|---|---|
| No movements recorded against this part yet. | |||||
Costing
- Material rolled up
- $3,502.40
- Labour (104 h)
- $12,272.00
- Standard cost
- $15,774.40
- Lead time
- 21 days
Where used