WO-2026-0354
CompleteACC-DP-140-6M — Drill Pipe 140 mm × 6 m × 24
Stock build · started 9 Feb 2026 · due 20 Mar 2026 · Ryan Beattie
Sell value
$130,440
At list
Material
$59,438
3 leaf lines
Labour booked
$23,600
200 h at $118.00
Hours vs plan
-5
200 booked of 205 planned
Margin as it stands
36.3%
$47,402 · quoted at $46,930
Routing
5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.
Operation 5 of 5
| Op | Operation | Work centre / supplier | Start | Finish | Planned h | Booked h | Var | By | Status |
|---|---|---|---|---|---|---|---|---|---|
| 10 | Cut and prep bar and tube | Cut & Prep Plasma table, band saws, drill line | Mon 9 Feb | Sat 14 Feb | 29 | 29 | 0 | — | Complete |
| 20 | CNC turn and mill | CNC Machining Horizontal borer, 2 × CNC lathe, VMC | Sat 14 Feb | Sun 1 Mar | 94 | 91 | -3 | RB | Complete |
| 30 | Heat treatment — harden and temper | Bodycote Australasia Outside operation · 12-day lead · 87% on time | Sun 1 Mar | Fri 13 Mar | — | — | — | EXT | Complete |
| 40 | Weld, hardface and dress | Fabrication Bay 2 Sub-assembly and accessory fabrication | Fri 13 Mar | Fri 20 Mar | 45 | 42 | -3 | RB | Complete |
| 50 | Assemble and inspect | Assembly Bay Rig build-up, 4 bays | Fri 20 Mar | Thu 26 Mar | 37 | 38 | +1 | RB | Complete |
Kit list — what this job consumes
The bill of materials flattened to its leaves for 24 × ACC-DP-140-6M. 3 lines, $59,438.40 of material. 2 can't be covered from free stock today.
| Part No. | Description | Source | Supplier | Required | Free | Unit | Extended |
|---|---|---|---|---|---|---|---|
| RAW-TUBE-219X16 | Seamless Tube 219 × 16 | Buy | Bohler Uddeholm Australia | 148.8 m | 12 | $326 | $48,509 |
| SUB-HT-4140 | Heat Treatment — 4140, harden & temper | Subcontract | Bodycote Australasia | 24 ea | 0 | $420 | $10,080 |
| CON-WIRE-ER70S | MIG Wire ER70S-6 1.2 mm | Buy | Cigweld | 72 kg | 424 | $12 | $850 |