WO-2026-0446
PlannedACC-SUB-API-114 — Substitute, API Reg 114 mm × 20
For Drillit International · against SO-2026-0149 · started 11 Aug 2026 · due 11 Sep 2026 · Nathan Poole
Sell value
$23,760
From SO-2026-0149
Material
$13,512
2 leaf lines
Labour booked
$590
5 h at $118.00
Hours vs plan
-65
5 booked of 70 planned
Margin as it stands
40.6%
$9,658 · quoted at $1,988
Routing
5 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.
Operation 1 of 5
| Op | Operation | Work centre / supplier | Start | Finish | Planned h | Booked h | Var | By | Status |
|---|---|---|---|---|---|---|---|---|---|
| 10 | Cut and prep bar and tube On now | Cut & Prep Plasma table, band saws, drill line | Tue 11 Aug | Sat 15 Aug | 10 | 5 | — | — | In progress |
| 20 | CNC turn and mill | CNC Machining Horizontal borer, 2 × CNC lathe, VMC | Sat 15 Aug | Thu 27 Aug | 32 | — | — | — | Planned |
| 30 | Heat treatment — harden and temper | Bodycote Australasia Outside operation · 12-day lead · 87% on time | Thu 27 Aug | Tue 8 Sep | — | — | — | EXT | Planned |
| 40 | Weld, hardface and dress | Fabrication Bay 2 Sub-assembly and accessory fabrication | Tue 8 Sep | Mon 14 Sep | 15 | — | — | — | Planned |
| 50 | Assemble and inspect | Assembly Bay Rig build-up, 4 bays | Mon 14 Sep | Sat 19 Sep | 13 | — | — | — | Planned |
Kit list — what this job consumes
The bill of materials flattened to its leaves for 20 × ACC-SUB-API-114. 2 lines, $13,512.00 of material. 1 can't be covered from free stock today.
| Part No. | Description | Source | Supplier | Required | Free | Unit | Extended |
|---|---|---|---|---|---|---|---|
| SUB-HT-4140 | Heat Treatment — 4140, harden & temper | Subcontract | Bodycote Australasia | 20 ea | 0 | $420 | $8,400 |
| RAW-4140-200RD | 4140 Round Bar Ø200 | Buy | Bohler Uddeholm Australia | 360 kg | 1,188 | $14 | $5,112 |