← Work orders
WO-2026-0449
PlannedBD-DPX-350 — Duplex Power Pump 350 × 1
Stock build · started 28 Sep 2026 · due 27 Nov 2026 · Vinnie Sultana
Note: Duplex pump for the Riteline hire fleet.
Sell value
$205,000
At list
Material
$59,334
21 leaf lines
Labour booked
$1,534
13 h at $118.00
Hours vs plan
-371
13 booked of 384 planned
Margin as it stands
70.3%
$144,132 · quoted at $70,264
Routing
10 operations. The ones with a supplier leave the building — Craig, that's the work you said you're now doing externally.
Operation 1 of 10
| Op | Operation | Work centre / supplier | Start | Finish | Planned h | Booked h | Var | By | Status |
|---|---|---|---|---|---|---|---|---|---|
| 10 | Cut, prep and drill plate and section On now | Cut & Prep Plasma table, band saws, drill line | Mon 28 Sep | Thu 1 Oct | 23 | 13 | — | — | In progress |
| 20 | Laser profiling — plate nest | Laser Cutting Services QLD Outside operation · 8-day lead · 95% on time | Thu 1 Oct | Fri 9 Oct | — | — | — | EXT | Planned |
| 30 | Robotic weld — mast box and chassis frame | Robotic Weld Cell Robotic welding — the 2024 workshop upgrade | Fri 9 Oct | Fri 16 Oct | 54 | — | — | — | Planned |
| 40 | CNC machining — spindle, gears, pins | CNC Machining Horizontal borer, 2 × CNC lathe, VMC | Fri 16 Oct | Thu 22 Oct | 42 | — | — | — | Planned |
| 50 | Heat treatment — harden and temper | Bodycote Australasia Outside operation · 12-day lead · 87% on time | Thu 22 Oct | Tue 3 Nov | — | — | — | EXT | Planned |
| 60 | Fabrication — mast, chassis, deck | Fabrication Bay 1 Mast and chassis fabrication | Tue 3 Nov | Sat 14 Nov | 85 | — | — | — | Planned |
| 70 | Assembly — drive, power pack, undercarriage | Assembly Bay Rig build-up, 4 bays | Sat 14 Nov | Thu 26 Nov | 92 | — | — | — | Planned |
| 80 | Hydraulics and electrical — hose, valve bank, IQAN | Hydraulics & Electrical Hose runs, valve banks, IQAN commissioning | Thu 26 Nov | Thu 3 Dec | 50 | — | — | — | Planned |
| 90 | Blast and 2-pack — Bournedrill navy | Paint Booth Blast and 2-pack, Bournedrill navy | Thu 3 Dec | Sat 5 Dec | 15 | — | — | — | Planned |
| 100 | Test and commission — load and function test | Test & Commission Load test, function test, sign-off — mints the serial | Sat 5 Dec | Tue 8 Dec | 23 | — | — | — | Planned |
Kit list — what this job consumes
The bill of materials flattened to its leaves for 1 × BD-DPX-350. 21 lines, $59,333.55 of material. 3 can't be covered from free stock today.
| Part No. | Description | Source | Supplier | Required | Free | Unit | Extended |
|---|---|---|---|---|---|---|---|
| ENG-CUM-QSF38 | Cummins QSF3.8 — 97 kW | Buy | Cummins South Pacific | 1 ea | 4 | $22,400 | $22,400 |
| HYD-PMP-A10VO-140 | Variable Pump A10VO 140 cc | Buy | Bosch Rexroth Australia | 2 ea | 6 | $7,420 | $14,840 |
| HYD-MOT-A6VM-160 | Hydraulic Motor A6VM 160 cc | Buy | Bosch Rexroth Australia | 1 ea | 9 | $7,400 | $7,400 |
| HYD-COOL-3B | Cooler Pack — 3 bank | Buy | Parker Hannifin Australia | 1 ea | 6 | $5,400 | $5,400 |
| SUB-LASER-PL | Laser Profiling — plate nest | Subcontract | Laser Cutting Services QLD | 2 ea | 0 | $680 | $1,360 |
| ELE-ALT-24V-100 | Alternator 24 V 100 A | Buy | Blackwoods | 1 ea | 7 | $960 | $960 |
| BRG-SPH-22320 | Spherical Roller Bearing 22320 | Buy | Motion Australia (CBC Bearings) | 2 ea | 15 | $416 | $832 |
| SUB-PC-GUARD | Powder Coat — guarding set | Subcontract | Queensland Powder Coating | 1 ea | 0 | $760 | $760 |
| HYD-FLT-RET-10 | Return Line Filter — 10 µm | Buy | Hydraulink Brisbane South | 2 ea | 18 | $340 | $680 |
| RAW-PL-350-12 | Plate 12 mm Grade 350 | Buy | InfraBuild Steel Centre | 263 kg | 4,380 | $2 | $644 |
| ENG-AIRCLN | Air Cleaner Assembly | Buy | Cummins South Pacific | 1 ea | 7 | $620 | $620 |
| HYD-HOSE-R2-12 | Hose 3/4" 2-wire R2 | Buy | Hydraulink Brisbane South | 14 m | 378 | $42 | $581 |
| CON-PNT-2PK-NAVY | 2-Pack Enamel — Bournedrill Navy | Buy | Dulux Protective Coatings | 8 L | 48 | $68 | $544 |
| ELE-BATT-N200 | Battery N200 24 V set | Buy | Blackwoods | 1 ea | 11 | $485 | $485 |
| SUB-HT-4140 | Heat Treatment — 4140, harden & temper | Subcontract | Bodycote Australasia | 1 ea | 0 | $420 | $420 |
| HYD-FIT-JIC-12 | JIC Fitting 3/4" straight | Buy | Hydraulink Brisbane South | 18 ea | 472 | $22 | $392 |
| CON-PRIMER-ZN | Inorganic Zinc Primer | Buy | Dulux Protective Coatings | 5 L | 116 | $54 | $270 |
| RAW-EN8-90RD | EN8 Round Bar Ø90 | Buy | Bohler Uddeholm Australia | 26 kg | 546 | $9 | $231 |
| RAW-TUBE-114X10 | Seamless Tube 114 × 10 | Buy | Bohler Uddeholm Australia | 1.8 m | 238 | $124 | $223 |
| SEA-KIT-GBX | Gearbox Seal Kit | Buy | Motion Australia (CBC Bearings) | 1 ea | 21 | $184 | $184 |
| CON-WIRE-ER70S | MIG Wire ER70S-6 1.2 mm | Buy | Cigweld | 9 kg | 424 | $12 | $106 |